Digging – Approximately 1 Week

After your pool has been designed and you’ve obtained the appropriate permits with your city – which can take anywhere from 3 to 10 weeks to complete – your pool company can actually start digging. The process of excavation usually takes somewhere around a week to do and involves removing the dirt in the area that you plan to install your pool. 

This can take less than a week to do, but you may want to add more time to account for any potential unforeseen issues that may arise, such as if there are any utility lines in the area that you are digging in. 

Plumbing, Electrical, and Laying Steel – Approximately 1 to 2 Weeks

Once the pool has been excavated, the steel will be laid, and the plumbing pipes and electrical wiring will be laid. Plus, there may be other things that go along with this process, such as setting up for your pool lighting, water features, and other amenities. Depending on how large the pool is and how detailed the design is, you could be looking at a couple of weeks for this process to be completed. 

Pool Installation – Approximately 1 to 3 Weeks

The actual installation of the pool can now take place, which can involve a number of things depending on exactly what type of pool you’re putting in. For instance, any fiberglass, plastering, concrete, or vinyl will be installed as per your specifications. This process can take anywhere from 1 to 3 weeks depending on the complexity of your pool design and materials used.  

Hardscaping and Landscaping – Approximately 1 to 4 Weeks

Once the actual pool has been installed, you’ll want to add all the details surrounding it, like the deck, other hardscaping, and greenery. Depending on the type of hardscaping and landscaping that you plan to install, the process can take anywhere from 1 to 4 weeks or longer. 

As you can see, the process of building a swimming pool can take anywhere from 2 to 3 months. To make sure you stick to the schedule, be sure to work with a trusted and reliable Austin swimming pool builder, like Reliant Pools!